Runway Closures

Runway Refurbishment 2010-2011

The work
Over 2010-2011 we carried out a £20 Million refurbishment programme on Runway 1 (Runway 23R/05L). 

The project involved:

  • The laying of 60,220 Metres of ducts
  • The replacement 110 Kilometres of cable
  • The construction of 370 Draw pits (man holes)
  • 23 major drainage repairs
  • The replacement of over 1,000 individual light fittings.
  • The resurfacing of the entire length (3,048m) and width (46m) of the runway.
  • Night time use of Runway 2 (Runway 23L/05R) to allow overnight works to take place on Runway 1.
  • A comprehensive communication strategy which commenced eighteen months before work started and was completed in March 2012.

Video
As a part of this project we compiled video clips to explain what work needed to be done and actual film of various stages of the work being carried out. Below are two video clips that are a review the project and our communication strategy for these works.

 

 

Contact us
If you have any questions or particular concerns that are not addressed by this page please e-mail the Community Relations Team. If you have any suggestions about how to improve this page please let us know.

Future runway closures
Please return to this page for information on future runway closures.

Last updated 30 March 2012